The construction and design of the FTTH access network cable in the Gostyń, Kalisz, Międzychód, Nowy Tomyśl, Poznan, Rawicz, Turek, Wolsztyn, and Września districts

The construction and design of the FTTH access network cable in the Gostyń, Kalisz, Międzychód, Nowy Tomyśl, Poznan, Rawicz, Turek, Wolsztyn, and Września districts

Execution of implementation and construction works involving construction of ducts, construction and commissioning of cable FTTH access networks, including intermediate access points for broadband investment areas in the villages of Dębsko, Kalisz County, Dziećmierowo, Głażewo, Gołaszyn, Gorzyn, Granowo, Jasin, Jutrosin Kębłowo, Łęczyca Łowyń, Michorzewo, Opalenica, Poniec, Porazyn, Przebędowo Pudliszki, Ruchocice, Ruda, Rudniki, Sierakowo, Sierzchów, Szczodrzykowo, Szulec, Uścięcice, Hungarian, Wielen, Zawada, and Żychlewo under 1 project co-financed by the European Union under the European Regional Development Fund:

“Providing broadband in selected villages in the Wielkopolska province”
(Project No. POIG.08.04.00-30-102 / 11 – dot. in villages Dębsko, Kalisz County, Dziećmierowo, Głażewo, Gołaszyn, Gorzyn, Granowo, Jasin, Jutrosin Kębłowo, Łęczyca, Łowyń, Michorzewo, Opalenica, Poniec, Porazyn, Przebędowo Pudliszki, Ruchocice, Ruda, Rudniki, Sierakowo, Sierzchów, Szczodrzykowo, Szulec, Uścięcice, Hungarian, Wielen, Zawada, and Żychlewo)

Performance of any construction, assembly, installation and finishing related to the implementation ducts, construction and commissioning of cable FTTH access networks, HFC, including intermediate access points for broadband subscriber connections and construction investment areas in the villages of Dębsko, Dziećmierowo, Głażewo, Gołaszyn, Gorzyń, Granowo, Jasin, Jutrosin, Kębłowo, Łęczyca, Łowyń, Michorzewo, Opalenica, Poniec, Porażyn, Przebędowo, Pudliszki, Ruchocice, Ruda, Rudniki, Sierakowo, Sierzchów, Szczodrzykowo, Szulec, Uścięcice, Węgierki, Wieleń, Zawada, and Żychlewo.

Ongoing
The number of sockets built 1100 pcs.
The length of the network constructed 27 km
Financing Project No. POIG.08.04.00-30-102/11

 